A new stretch of canal at Wichelstowe is beginning to look like the finished article, with much of the construction work now complete and rainwater naturally filling the channel.
The 600-metre stretch of the Wilts & Berks Canal forms part of the ongoing development in the south of Swindon, where up to 4,500 homes will eventually be built.
More than £5 million is being invested in the current phase of canal and bridge works, which will see the waterway extend south from the Wichelstowe district centre before turning east towards Mill Lane.
Councillor Matty Courtliff, Swindon Borough Council’s Cabinet Member for Housing and Property, visited the site on Tuesday, 24 November, to see how work was progressing.
Much of the canal bed has now been lined with clay, allowing rainwater to gradually fill the channel, while work on the surrounding infrastructure is also moving forward.
A new road alongside the canal is due to be surfaced in December, while cladding and stone-filled gabion baskets have been installed on the canal bridge.
The latest developments follow the installation of the Bushey Fox swing bridge earlier this year, with contractor Fox (Owmby) Ltd carrying out the current phase of restoration work.
Cllr Courtliff said: “The canal has always been one of the most distinctive parts of the vision for Wichelstowe, so it’s fantastic to see just how much progress has been made.
“What was recently a construction site is now beginning to look and feel like a real canal, with water naturally filling the channel and key infrastructure taking shape around it.
“The restoration of the Wilts & Berks Canal is helping to create a place with its own identity and character, while providing future opportunities for walking, cycling, wildlife and leisure.
“The progress being made is a real credit to all those working on site and I look forward to seeing the next milestones reached over the coming year.”
What comes next for Wichelstowe?
The current phase of work is expected to be largely complete in 2027, with attention then turning to further road connections and extending the canal beneath Mill Lane.
Rob Powe, Development Manager for Wichelstowe LLP, said: “It’s exciting to see the canal beginning to fill with water as the project continues to take shape.
“The majority of the canal lining work has now been completed and we have also made excellent progress on the associated road and bridge infrastructure.
“Works will be largely complete in 2027, after which we will focus on delivering the Wichel Way link to Scott Way roundabout and the canal crossing beneath Mill Lane, helping to bring another important part of the Wichelstowe vision to life.”
One of the largest housing developments in the South West, Wichelstowe will eventually include schools, employment space, leisure facilities and extensive green spaces alongside its 4,500 planned homes.
Restoring sections of the historic Wilts & Berks Canal remains central to those plans, creating a waterside setting for residents and opening up future opportunities for walking, cycling and leisure.
Further information about the development can be found on the Wichelstowe website.
Details of the wider canal restoration project can also be found on the Wilts & Berks Canal Trust website.