A new stretch of canal at Wichelstowe is beginning to take shape, with most of the channel now complete and rainwater starting to fill the newly constructed waterway.
The project, which forms part of the wider Wichelstowe development, marks another step forward in the restoration of the historic Wilts & Berks Canal.
Councillor Matty Courtliff, Swindon Borough Council’s Cabinet Member for Housing and Property, visited the site on 24 November to see how work is progressing on the latest section, being delivered by contractor Fox (Owmby) Ltd.
The new stretch runs south of Wichelstowe’s district centre. Most of the canal channel has now been lined with clay, allowing rainwater to collect naturally as construction work continues.
Alongside the waterway, work is also progressing on the surrounding infrastructure. The new road is expected to be surfaced next month, while the canal bridge has reached another milestone, with its cladding and gabion basket installation now complete.
The latest work follows the installation of Bushey Fox Bridge, the development’s swing bridge, earlier this year.
More than £5 million is being invested in this phase of the project, which includes a new 600-metre section of canal. The route will extend south from the district centre before turning east towards Mill Lane.
Cllr Courtliff said seeing the canal begin to fill with water was an encouraging sign of how far the project had come.
He said the waterway had always been one of the most distinctive features of the plans for Wichelstowe, adding that it was now starting to look and feel like a real canal rather than a construction site.
He also pointed to the opportunities the restored waterway could bring for walking, cycling, wildlife and leisure, as well as giving the development its own identity.
Rob Powe, Development Manager for Wichelstowe LLP, said the majority of the canal lining had been completed and progress on the road and bridge infrastructure had also been good.
Works are expected to be largely complete during 2027.
After that, attention will turn to the Wichel Way link to Scott Way roundabout and the canal crossing beneath Mill Lane, completing further connections within the development.
Wichelstowe is one of the largest residential developments in the South West and is expected to deliver up to 4,500 homes when complete.
The wider plans also include schools, employment space, leisure facilities and green spaces.
The restoration of the Wilts & Berks Canal is a central part of that vision, bringing back a section of the historic waterway and creating a waterside setting for people living in and visiting the area.
While there is still work to be done, the sight of water beginning to fill the new channel offers a clearer picture of what this part of Wichelstowe will eventually look like.